Julius Berger shuts Lagos-Shagamu expressway, creates road diversion on Monday 

Published

Julius Berger announces road diversion, to shut Lagos-Shagamu expressway on Monday 



Construction company, Julius Berger Nigeria Plc, has announced a major road diversion on Lagos–Shagamu Expressway to allow for detailed work on sections of the project.

This is just as the company discloses that it will close sections of the Lagos-Shagamu expressway to facilitate repairs.

In a statement issued on Friday, the project team said that there will be traffic diversion at two locations of the expressway for the continuation of the ongoing bridge works at Eldorado and Lotto Junction, respectively.

The Eldorado diversion will take place in two phases.

The first phase will be implemented between July 26 and 30 while the second phase will take place from August 9 to November 9.

MORE READING!  Military frees abducted Lagos editor Segun Olatunji

The construction firm said traffic would be diverted for road users plying the route from different parts of the state.

“Phase 1 will include temporary diversion of traffic on Ibadan bound carriageway, from a section before Eldorado, CH 37+500 to a section after Eldorado, CH 37+900 (400m stretch),” the statement reads.

“This will take place between July 26, 2021 and July 30, 2021 for the installation of cross beams on both sides of the expressway, after which both sides of the expressway will be reopened to traffic.

MORE READING!  Super Eagles suffer 2-0 defeat to Mali

“In addition, beginning from August 9, 2021 through to November 9, 2021, Phase 2 of the diversion will be implemented for the installation of deck slabs, parapets and hand railings on both sides of the Eldorado flyover.

“Also, effective from July 30, 2021, Lagos bound traffic will be diverted to the Ibadan bound carriageway, from a section before Lotto Junction, CH 24+800 to a section at Deeper Life Conference Centre, CH 23+800, with two lanes each in opposite direction using temporary median dividers.

“The purpose of the diversion is to allow for the safe installation of cross beams, bridge deck slabs and parapets on the ongoing bridge works on the Ibadan bound carriageway, which will last for 12 weeks.”

MORE READING!  Police neutralise two notorious bandits in Benue

“Such mitigating measures will include, display of advanced warning signs for road narrowing and for necessary speed restriction,” he said.

“Julius Berger LSE Project Team will provide Flagmen and suitable illuminated diversion points at night, including flashing lights and sufficient reflective road signs.

“Julius Berger emergency response crew will be on standby for a 24/7 emergency response services with well-established lines of communication between various agencies including the Nigerian Police, FRSC, TRACE and other relevant stakeholders that have emergency response teams.”

 